中心城区轨交站点施工区域合流总管迁改及加固设计
作者:
作者单位:

作者简介:

通讯作者:

中图分类号:

基金项目:


Author:
Affiliation:

Fund Project:

  • 摘要
  • |
  • 图/表
  • |
  • 访问统计
  • |
  • 参考文献
  • |
  • 相似文献
  • |
  • 引证文献
  • |
  • 资源附件
  • |
  • 文章评论
    摘要:

    中心城区现状道路下方各类市政管线非常密集,而轨道交通站点基坑的大开挖施工范围内所有管线都需进行迁改,尤以大型排水管道的迁改最为复杂,且因涉及到临时排水,迁改费用通常较高。以上海市轨道交通14号线工程东新路站建设为例,结合轨交站点总体设计,在武宁路(凯旋北路-普雄路)对Φ2400合流污水总管进行永久迁改,并对局部节点进行预加固和临时排水,确保轨交站点的顺利建设。

    Abstract:

    Various municipal pipelines under the existing roads in the central urban area are very dense, and all pipelines within the construction scope of the large excavation of the foundation pit of the rail transit station need to be relocated, especially the relocation of large-scale drainage pipelines is the most complicated, and because it involves temporary drainage , the cost of relocation is usually higher. Taking the construction of Shanghai Rail Transit Line 14 Project Dongxin Road Station as an example, combined with the overall design of the rail transit site, the Φ2400 combined sewage main pipe was permanently relocated on Wuning Road (North Kaixuan Road-Puxiong Road), and some The nodes are pre-reinforced and temporarily drained to ensure the smooth construction of rail transit stations.

    参考文献
    相似文献
    引证文献
引用本文

姚陈珏.中心城区轨交站点施工区域合流总管迁改及加固设计[J].城市道桥与防洪,2022,(7):99-102.

复制
分享
文章指标
  • 点击次数:
  • 下载次数:
  • HTML阅读次数:
  • 引用次数:
历史
  • 收稿日期:2022-03-15
  • 最后修改日期:2022-03-15
  • 录用日期:2022-03-20
  • 在线发布日期: 2022-07-21
  • 出版日期:
关闭